Gig City program almost finished installing cables

By Daniel Olson 3 min read
A worker pumps into a drilled hole. Fiber internet cable connections to homes and businesses will only be made with owner consent.

NEW ULM-- NUVERA's Gig City project is operating at faster speeds then anticipated, and could complete its initial goals two years ahead of schedule.

The project seeks to install fiber internet cables throughout the entirety of New Ulm as well as parts outside the city limits. Initially projected to finish by 2026, NUVERA CEO Glenn Zerbe now projects their initial goals to be completed by 2024 at the earliest.

"We plan in the next year, maybe two years to finish the last 700 to 1000 homes and businesses to complete the project," he said. "We are ahead of schedule, and working diligently and judiciously through the community. It’s a balancing act you have to do. There’s a lot of things to sequence, including the utility companies and others. To locate all the facilities, you have to dig some things up. There’s an urgent pace, but there’s also a pace to keep everybody not feeling like we’re tearing up the city to provide broadband services. We feel like we’re in a pretty good place here."

The construction to install these cables comes in two steps. Zerbe explained these steps and what they mean for the people of New Ulm.

"First of all, we’re passing all the homes. There’s going to be fiber going in the right of way down in front of your home. That’s unavoidable," he said "Then there’s a second step, to build from the right of way or the street in your home. If you are a current customer of ours, we’re going to build at no cost. For customers who pre-buy from us, we’ll do the same thing. If you choose not to buy from us and you’re not a customer, we won’t be building to your home."

After construction is completed, any necessary restoration will be handled by NUVERA at no cost to the owner. Zerbe believes the biggest benefit to this project is making sure New Ulm's infrastructure is modern and stable.

"These are modern day roads, utilities, bridges and whatever might be important to community infrastructure," he said. "We think this infrastructure is multi-decade, maybe [last] as long as 30-40 years. There’s no better communications methodology then fiber available today. We think when we’re done here with this part of our project, homes [and businesses] will be future-proofed for infrastructure on connectivity to the world for decades to come."

Even when the initial goals are complete, NUVERA is looking toward the future. Zerbe said they are committed to continued expansion of fiber internet. "While we started in many ways here in New Ulm, it has propagated quickly out from there," he said. "Even though our original project is wrapping up, we will be continuing to go across southern Minnesota for years to come."

Those who wish to get in on the project and have not already opted-in need to opt-in now for the cables to be installed at no cost. Information can be found at nuvera.net/construction or by calling 507-354-4111.